Dai Tu invests lighting system on National Highway 37

Thu Huyen 14:06, 08/09/2023

To ensure urban aesthetics, public safety, and traffic safety, and to gradually complete the criteria of a civilized urban area, Dai Tu district has invested over 4.6 billion VND to construct a lighting system on National Highway 37, spanning through Cu Van commune and Ha Thuong commune, with a total length of over 7,000 meters, from kilometer 140+900 to kilometer 148+130. 

 

As a part of this project, 187 lighting columns have been erected. These lamp posts are positioned on the right side of the road (in the direction from the Bo Dau intersection to Dai Tu district) at a distance of 6.65 to 7.75 meters from the road's center. Four lighting control cabinets have been installed and interconnected to automate the lighting system. The electrical columns are 10 meters and 12 meters tall centrifugal concrete columns.

This project falls under group C, a grade IV technical infrastructure project. The district commenced the project in mid-July 2023. The project has been completed and put into operation ahead of schedule by 3 months.